East Arnhem Real Estate has engaged contractors to conduct maintenance and other works on 85 Chesterfield Circuit, on and around Gove Cafe. This will include pressure cleaning, sealing of windows and painting. The schedule of works is below:

  • 03/09- 06/09: internal common areas incl. toilets

  • 07/09 – 08/09 (weekend 1): pressure wash side and front walls, windows and shade sails

  • 09/09 – 12/09: rear wall painting and sealing windows

  • 13/09: side wall painting

  • 14/09 -15/09 (weekend 2): front level 1 wall painting and sealing windows, ceiling painting

  • 16/09 – 20/09: front ground level wall painting and sealing windows